Washington State School for the Blind Ten-Year Plan
|
Project
Number |
OFM
Priority |
Description |
Cost |
|
2003-2005 |
1 |
Irwin, Old Main, Kennedy & Dry
Building Re-appropriation of funds to complete preservation work in the
Kennedy Physical Education Building |
$300,000 |
|
2003-2005 |
2 |
Ahlsten-Material Center/Covered
Play Area Re-appropriation of funds to complete the construction of the
Ahlsten-Material Center & Braille Production |
$300,000 |
|
2003-2005 |
3 |
Distance Learning Center/Covered
Play Area Re-appropriation of funds to complete the project. |
$500,000 |
|
2003-2005 |
4 |
Campus Preservation
Re-appropriation of funds to complete general campus preservation work which
can not be completed as a result of delays with other capital projec |
$200,000 |
|
2003-2005 |
5 |
Renovation of the Boiler House and
replacement of two major electric vaul |
$668,000 |
|
2003-2005 |
6 |
General Campus preservation – tech
infrastructure, painting, heating/cooling, energy management, parking lot
sealing, minor pool renovations. (preservation) |
$770,000 |
|
2003-2005 |
7 |
Replacement and installation of
commercial kitchen in the Old Main annex (program) (this was not funded at this
time) |
$425,000 |
|
2003-2005 |
8 |
Preservation work on Kennedy, Dry,
and Irwin - final phase-most work will occur on Kennedy– physical education
building & Dry–vocational education facility. Small amoun |
$2,279,000 |
|
2003-2005 |
9 |
Independent Living Uni |
$471,000 |
|
2005-2007 |
6.1 |
General Campus Preservation–Roofing
rejuvenation, heating system, energy management, security, lighting, tech.
infrastructure, flooring replacement, parking lot sealing (preservation) |
$730,000 |
|
2005-2007 |
10 |
Cottage Renovation (program) |
$1,756,000 |
|
2007-2009 |
6.2 |
General Campus Preservation –
energy management, security, HVAC work, roofing rejuvenation, tech.
infrastructure, lighting (preservation) |
$700,000 |
|
2009-1011 |
6.3 |
General Campus
Preservation–Technology infrastructure, fencing/gates, sidewalk replacement/ADA,
security, roofing rejuvenation, heating systems, parking lo |
$700,000 |
|
2011-2013 |
6.4 |
Kennedy Bldg – pool renovation (preservation)
- Equipment replacement, conditioning or possible
replacement of the pool liner. Deck
conditioning and upgrades to provide for the safety of children. Additional
work will need to be done on the HVAC system, which includes a humidity
control system. Note: This future
work would not be necessary with replacement of the |
$700,000 |